Data center commissioning: Levels 1 to 5, integrated systems testing and commissioning companies

Data center commissioning is the owner's quality process for proving that power, cooling, controls and life safety systems work, alone and together, before IT load goes in. ASHRAE describes the sequence as Level 1 factory acceptance testing, Level 2 delivery and installation checks, Level 3 pre-functional checks, Level 4 functional performance testing of each system and Level 5 integrated systems testing (IST).1 Firms number and name the stages differently, so write your scope by activity, not by level number. ASHRAE's data-center-specific guideline (1.6P) is still a proposed project, so the published process documents are ASHRAE/IES Standard 202-2024 and Guideline 0-2019.24 Below: what each level tests, an IST load bank planner, credentials you can verify, and 11 firms whose own sites say they do this work, unranked. We're a directory and referral service, not a commissioning agent.

Updated · How we research

What data center commissioning covers, and what it isn't

Commissioning verifies that the facility and its systems meet the Owner's Project Requirements (OPR), with documentation at each phase from predesign through occupancy and operations; it is a process, not one test.3 ASHRAE's proposed data center guideline is scoped to the support infrastructure, not to IT equipment and networks.2

Three related activities get confused with it:

  • Manufacturer start-up. The equipment maker's representative starts its own unit; the commissioning team checks that it was done properly.8
  • Electrical acceptance testing. Tests that installed electrical equipment is operational, within tolerances and installed to design, for example to ANSI/NETA ATS (current edition ATS-2025).14 Ask how your CxA will witness or review those results.
  • Tier certification. Uptime Institute's Tier Certification of Constructed Facility (TCCF) is a separate award based on live demonstrations; Uptime typically visits right after Level 5 commissioning.1213

The five commissioning levels and what each one tests

Each level is a gate: equipment moves to the next one only after the previous level's checks are signed off. Some firms mark equipment with a colored tag at each gate: red after Level 1, yellow after Level 2, green after Level 3, blue after Level 4 and white after Level 5.79

Data center commissioning levels 0 to 6 A vertical ladder. Level 0 design and planning, no tag. Level 1 factory witness testing, red tag. Level 2 delivery and installation, yellow tag. Level 3 start-up and pre-functional checks, green tag. Level 4 functional performance testing of each system, blue tag. Level 5 integrated systems testing, white tag. Level 6 turnover, no tag. A bracket shows levels 1 to 3 led by the contractor and levels 4 to 6 led by the owner's commissioning agent in one published scheme. L0 Design and planning L1 Factory witness testing L2 Delivery and installation L3 Start-up, pre-functional L4 Functional performance L5 Integrated systems test L6 Turnover Design review, Cx plan · no tag At the factory · red tag Matches submittals · yellow tag Energize, start · green tag Each system · blue tag Load + failures · white tag Final report, handover · no tag Contractor-led Owner's CxA-led
Levels and tag colors as Construct & Commission publishes them (CxPlanner uses the same Level 1 to 5 colors). The contractor/CxA split is Construct & Commission's; your contract decides who leads each level.79
What each commissioning level checks, with examples from published programs. Sources: ASHRAE (level definitions), Construct & Commission, IPS and Universal Load Banks (examples).
LevelWhat it provesTypical checks (examples)
L1 FactoryMajor equipment meets the specification before it ships.1Factory tests of generators (kW/kVA), UPS modules, coolant distribution unit (CDU) heat-transfer capacity and controls; QA/QC inspection of equipment that isn't tested.117
L2 Delivery and installationWhat arrived is what was approved, undamaged, and installed to the drawings.17Delivery inspection against submittals; in some programs also static tests such as pressure testing, pipework cleaning, rotation checks, dead testing and earthing tests.87
L3 Start-up and pre-functionalIndividual components and subsystems are confirmed ready for operation.1Wiring, ductwork and piping checks; power and rotation; pressure hold and leak checks; cleaning and flushing; manufacturer start-up checks; settings entered and validated.87
L4 Functional performanceEach system performs fully on its own, under various conditions.1Operating modes, interlocks and sequences of operation; UPS bypass, battery discharge, generator step load, pump staging. Systems include electrical distribution, emergency power, UPS, chillers, the building automation system (BAS), fire alarm and suppression.7118
L5 Integrated systems testingAll systems work together under real-world and failure scenarios.1Utility loss, generator failure, UPS loss, chiller/CDU/pump failure; electrical integrated testing, load bank and heat load testing; BAS and monitoring of in-operation conditions.118

Many programs add Level 0 (design and planning) and Level 6 (turnover); IPS also adds Level 7 (operational readiness).678

How level names differ between sources

Levels 1, 4 and 5 mean the same thing almost everywhere; Levels 2 and 3 do not. Some programs put installation inspection and static pre-commissioning tests in Level 2, while others limit Level 2 to delivery inspection and put installation checks in Level 3.78 That is why a contract that only says “Cx Levels 1 to 5” can leave gaps. List the activities you expect at each gate.

Commissioning level names in five published sources, checked November 27, 2026. A dash means the source doesn't name that level.
LevelASHRAE1JLL6Construct & Commission7IPS8CXT Engineering10
L0–Programming and designDesign and planningPlanning and design review–
L1Factory acceptance testingFactory acceptanceFactory testingPre-delivery inspections and factory testing (plus L1+ modular factory testing)Factory witness testing
L2Delivery and installation verified on siteSite acceptance testingComponent delivery, installation and pre-start-upPre-installation verificationSite acceptance inspection
L3Pre-functional checksStart-up and pre-functionalSystem start-upPre-functional testingPre-functional testing
L4Full functional performance of each systemFunctional performance testingFunctional performance testingFunctional testingFunctional performance testing
L5Integrated systems testingIntegrated systems testingIntegrated system testingIntegrated system testingIntegrated systems testing (IST)
L6–Transition to operationsCloseout, turnover, handoverClose-out, handover, owner acceptance–
L7–––Operational qualification and readiness–

Data center levels and ASHRAE's process aren't rivals. The levels are a testing sequence; ASHRAE's Guideline 0 and Standard 202 set out the process and documentation around it, starting from the OPR.3 Construct & Commission says that across multiple data center providers it has yet to see an OPR, basis of design or systems manual.7 A sound scope asks for both.

Integrated systems testing (Level 5) and load banks

IST runs the finished facility as one system: simulated IT load is applied, then failures are introduced to prove that power, cooling and controls respond as designed. A common Level 5 test is a blackout, or full power failure, to confirm the UPS carries the load and the generators start as designed.9 Load banks stand in for IT equipment because owners won't expose production servers to unproven utility feeds, generators, UPS systems, cooling plants or control sequences; a load bank draws measurable power and produces a known heat load.11

Typical Level 5 scenarios and what each proves. Sources: Universal Load Banks white paper (Nov. 2026), IPS, CxPlanner.
ScenarioWhat should be proven
Utility loss (blackout)UPS carries the load through the transfer; generators start and take load; recovery to normal once utility returns.911
Generator or UPS module lossRedundant capacity supports the applied load during a single failure.11
Chiller, CDU or pump failure; loss of facility waterAir or coolant temperature, flow and pressure stay within design limits while redundant equipment takes over.11
Heat load test in the data hallThe data hall's thermal response stays within design tolerances under different heat loads and failure scenarios.78
Controls and monitoringThe building management system (BMS), electrical power monitoring system (EPMS) and data center infrastructure management (DCIM) software detect each event, run the intended sequence and keep a time-stamped record.118

Liquid-cooled halls need liquid-cooled load

Air-cooled load banks put the heat in the wrong medium for a liquid-cooled hall: they can test the electrical path while leaving the CDUs, manifolds and coolant loop largely unproven. Liquid-cooled load banks draw real electrical power and transfer the heat into the technology cooling system (TCS), so one test exercises both paths; for hybrid halls, the plan should reproduce the expected air/liquid split.11 Cleanliness matters as much as capacity. ASHRAE warns that proper cleaning, flushing and passivating of hydronic systems, especially the TCS, should never be compromised for speed.1 For the cooling architecture itself see the liquid cooling guide, and for loop chemistry see closed-loop and cooling water treatment.

Medium-voltage testing

On large campuses, testing at 13.8 kV or 35 kV needs far less current and temporary cabling than testing the same megawatts at 480 V. Universal Load Banks puts a 20 MW resistive test at about 24,056 A at 480 V versus about 837 A at 13.8 kV, and says direct-connect medium-voltage banks prove upstream megawatts but not hall-level thermal performance, so both are needed.11

Where Uptime Tier certification fits

If you're pursuing Uptime's Tier Certification of Constructed Facility, plan for it during commissioning. Uptime requires Tier Certification of Design Documents first, and the constructed-facility award includes live system demonstrations.12 In a 2016 Uptime Institute Journal article, Uptime said its site visit typically comes immediately after Level 5 commissioning, that prepared clients have their own technical staff run rehearsed demonstrations, and that it asks for the commissioning schedule as an indicator of how rigorous commissioning has been.13

Plan IST load banks and coolant flow

Enter the IT load you plan to simulate and how much of it is liquid-cooled. The planner splits the load between air- and liquid-cooled load banks, counts units, and gives line current and coolant flow for 25%, 50%, 75% and 100% steps, a common staged sequence.11 Worked example (the defaults): 2,000 kW with 60% to liquid is 800 kW air-side (16 × 50 kW banks) and 1,200 kW liquid-side (2 × 750 kW units). At 480 V and unity power factor, full load draws about 2,406 A; the liquid share at a 10 °C rise needs about 1,728 L/min (about 456 gpm) of water.

IST load bank and coolant-flow planner

Planner

Air-side load

800 kW

Liquid-side load

1,200 kW

Air-cooled banks

16 × 50 kW

Liquid-cooled units

2 × 750 kW

Current at 100%

2,406 A

Liquid flow at 100%

1,728 L/min (456 gpm)

Load steps for the inputs above: kW, line current in amperes and liquid-side flow in liters per minute at the set ΔT
StepTotal kWAir / liquid kWLine current (A)Flow at set ΔT (L/min)
25%500200 / 300601432
50%1,000400 / 6001,203864
75%1,500600 / 9001,8041,296
100%2,000800 / 1,2002,4061,728

How it works: the test load is split into an air-side share and a liquid-side share. Units needed = share ÷ unit rating, rounded up, with no spare units added. Line current = kW × 1,000 ÷ (√3 × volts × power factor), for a balanced three-phase load at one connection point. Liquid flow uses Q = ṁ × cp × ΔT with water (cp 4.18 kJ/kg·K, 0.997 kg/L); glycol mixtures have a lower specific heat and need more flow, so ask the load bank supplier for the figure at your fluid. The step table holds ΔT constant; if your plan holds flow constant instead, ΔT falls with load. Planning aid only: it doesn't size cables, temporary distribution, protection or the cooling plant, and it isn't engineering advice. The 750 kW default matches one standard liquid-cooled load bank model a manufacturer lists; check ratings with your supplier.11

Give the result to whoever writes the load bank plan (a section ASHRAE's draft data center guideline was planned to include) so the rental fleet, temporary power and fluid connections are ordered early.5

Who does what: owner, commissioning agent, designers, contractor and OEMs

The owner hires the commissioning agent (CxA) and sets the requirements; the contractor and manufacturers build, start and fix; the CxA plans, witnesses and reports. ACG describes CxAs as independent professionals who work on behalf of building owners.15 In one published scheme the general contractor manages Levels 1 to 3 and the owner's commissioning consultant manages Levels 4 to 6, supported by the contractor.7

Owner and operations team

Owns the OPR, the requirements everything is checked against.3 ASHRAE recommends putting operators into Level 4 and 5 testing and validating methods of procedure (MOPs) there, because operator training is often squeezed out at the end.1

Commissioning agent (CxA)

Manages the commissioning project, prepares commissioning documentation, conducts commissioning activities and coordinates operator training, in ACG's description.15 ASHRAE recommends discipline subject-matter experts on site every day of commissioning and a dedicated commissioning scheduler.1

Design team

Documents the design intent in the basis of design (BoD) and resolves design issues. ASHRAE recommends the CxA review the design in real time rather than only at milestones.15

General contractor and trades

Installs, completes QA/QC and pre-start-up checks, and coordinates start-up. ASHRAE suggests dedicated start-up and troubleshooting teams so issues get fixed while testing moves on.71

Manufacturers (OEMs)

Run factory tests at Level 1 and start their own equipment at Level 3.78 For CDUs, chillers and other cooling equipment, see the cooling companies directory.

Specialists

Electrical testing firms (ANSI/NETA ATS), load bank suppliers, and Uptime Institute if you pursue Tier certification.141112

The commissioning documents you should get

Ask for these by name in the contract; they are how you check the work later. The list follows the sections planned for ASHRAE's data center guideline and the deliverables commissioning firms publish.5217

Core data center commissioning documents and their purpose. Sources: ACHR News on the planned ASHRAE Guideline 1.6 sections; ASHRAE bookstore; Ascent and Construct & Commission deliverable lists.
DocumentWhat it's for
Owner's Project Requirements (OPR)The owner's requirements and acceptance criteria that everything is verified against.35
Basis of design (BoD)The designers' explanation of how the design meets the OPR.521
Commissioning plan and specificationsThe plan sets scope, roles, responsibilities and procedures; the specifications carry commissioning requirements into the construction documents.521
Design and submittal review reportsIssues found on paper, before equipment is bought or built.5
Factory witness test procedures and reportsLevel 1 results per piece of equipment.57
Pre-functional checklistsLevel 2 and 3 installation and start-up records.21
Functional and IST scriptsStep-by-step test procedures with expected results, written and approved before testing.217
Load bank planWhere load goes, how much, how it's powered and cooled.57
Issues logEvery deficiency, who owns it and how it was closed, carried across all levels.217
Systems manual and training recordsHow the facility is meant to run; ASHRAE Guideline 1.4-2019 covers preparing systems manuals.45
Final commissioning reportConsolidated results, open items and recommendations at turnover.57

The systems manual and issues log feed straight into the facility's preventive maintenance program after turnover.

Standards and guidance: what exists and what doesn't yet

There is no published ASHRAE standard or guideline specific to data center commissioning yet. ASHRAE lists Guideline 1.6P, Commissioning of Data Centers, as a proposed guideline (project approved November 4, 2017) meant to help apply Guideline 0 or Standard 202 to data centers.23 ASHRAE's Titles, Purposes and Scopes page also records a June 2024 title amendment, to Application of the Commissioning Process to Data Centers; the SSPC 300 committee page still shows the original title.23 ASHRAE's description of Levels 1 to 5 appears on its AI data center framework web page, not in a published standard.1

Commissioning standards and guidance relevant to data centers, status as checked November 27, 2026. Sources: ASHRAE, NETA and Uptime Institute pages cited in each row.
DocumentPublisherStatusWhat it covers
Standard 202-2024, The Commissioning Process Requirements for New Buildings and New SystemsASHRAE/IESPublishedThe commissioning process for new buildings and systems, the roles of the principal agents, and documentation and reports.4
Guideline 0-2019, The Commissioning ProcessASHRAEPublishedRecommends measures beyond Standard 202's minimum, from predesign to occupancy and operation.43
Guideline 1.6P, Commissioning of Data CentersASHRAEProposedApplying Guideline 0 or Standard 202 to data center support infrastructure, not IT equipment.2
Standard 230-2022, Commissioning Process for Existing Buildings and SystemsASHRAEPublishedCommissioning existing buildings, with an owner-defined scope.4
ANSI/NETA ATS-2025NETAPublishedAcceptance testing of electrical power equipment and systems.14
Tier Certification of Constructed FacilityUptime InstituteCertification programLive demonstrations against the Tier Standard: Topology.12

ASHRAE's SSPC 300 committee page still headlines Standard 202 as the 2018 edition; the ASHRAE bookstore sells the 2024 edition.34

Schedule and cost: what drives them

Commissioning runs from design to turnover, but Levels 4 and 5 sit at the end of the schedule, where delays elsewhere land. ASHRAE notes that rapid AI builds put pressure on activities at the tail end of the project, “namely commissioning,” and that teams are turning over smaller blocks of infrastructure to start testing earlier, which needs closer coordination and tracking.1 Factory testing protects the schedule too: issues found at Level 1 can be resolved before the equipment leaves the factory.8

What the only published cost benchmark says

We found no credible published figure for data center commissioning cost as a share of construction cost. The closest benchmark is for commercial buildings in general. A Lawrence Berkeley National Laboratory and BCxA meta-analysis found new-construction commissioning cost a median 0.25% of construction cost in its 2018 sample and 0.57% in its 2009 sample (0.37% across all 140 projects); the median was $1.03 per square foot across all projects, with a 25th to 75th percentile range of $0.53 to $2.21, in 2017 dollars.20 Treat that as context, not a budget: those projects weren't data centers, and in our view a data center program with factory witness trips, load bank rental and IST carries scope that most commercial projects don't.

What moves a data center commissioning fee

  • Which levels are in scope, and whether the CxA writes the scripts or only reviews contractor scripts.
  • Number of factory witness tests and their locations.
  • Equipment count and whether sampling is allowed below Level 4.
  • Number of turnover blocks or phases, since each one repeats some testing.
  • Load bank fleet, temporary power and, for liquid-cooled halls, liquid-cooled units and fluid handling.11
  • Medium-voltage testing and Tier certification demonstrations.
  • On-site staffing: ASHRAE recommends discipline experts on site daily and a dedicated scheduler on fast projects.1
  • Operator training, MOP validation and the systems manual.

How to choose a data center commissioning agent

Choose on data center Level 4 and 5 experience, independence and staffing first, then check credentials. A certification shows a person knows the commissioning process; it doesn't show they've run an IST on your kind of plant.

Commissioning credentials you can check, with issuer, accreditation and eligibility, as each issuer's own page states them, checked November 27, 2026.
CredentialIssuerAccreditation or recognitionEligibility (summary)
CxA (Certified Commissioning Authority)ACG, the AABC Commissioning GroupANAB-accredited; recognized by DOE Better BuildingsFor professionals who lead commissioning teams; ACG describes CxAs as independent and working on behalf of owners. ACG publishes a CxA directory.15
CCP (Certified Commissioning Professional)Building Commissioning Certification Board (BCxA's sister organization)ANAB, under ISO/IEC 17024:2012; first certification recognized under the Better Buildings Workforce GuidelinesEducation plus experience, e.g. licensed PE or architect with 3 years' commissioning, or a building-science bachelor's with 5 years; an exam; recertification every 3 years. Public registry.1617
BCxP (Building Commissioning Professional)ASHRAEANAB, under ISO/IEC 17024 (#1139); recognized by DOESame education and experience tiers, participation in 3 commissioning projects and an exam. ASHRAE lists certificants.18
NEBB Building Systems CommissioningNEBBNEBB certification of firms and individualsCertified firms must have operated 12 months, provide six endorsement letters from building owners or contract awarding authorities, belong to a local NEBB chapter, own the required instruments and name a Designated Certified Professional.19

To check a name, use ACG's CxA directory, the BCCB public registry or ASHRAE's certificant list, all linked from the issuers' pages in Sources.151618 For electrical testing subcontractors, ask whether acceptance tests follow ANSI/NETA ATS.14

Questions to put in the request for proposal

  1. Who holds the contract? An owner-hired CxA reports to you. If commissioning sits under the contractor, ask who witnesses and signs off Level 4 and 5.157
  2. Show recent IST work. Ask for a redacted IST script, an issues log and a final report from a facility similar in size and cooling type.
  3. Staffing. Which electrical, mechanical and controls specialists will be on site, and on which days? Is there a dedicated commissioning scheduler?1
  4. Design-phase role. Will they review the design continuously or only at milestones?1
  5. Load bank plan. Who writes it, who rents the banks, and how liquid-cooled load and fluid cleanliness are handled.11
  6. Level definitions. Ask them to list the activities at each level, so Level 2 and 3 gaps show up before contract.78
  7. Tier certification. If you're pursuing TCCF, have they prepared sites for Uptime's demonstrations?13

Data center commissioning companies (unranked directory)

How this list was built

We started from the Google results for “data center commissioning” and “data center commissioning companies” on November 26, 2026, then read each company's own website. A company is listed only if its own site says it provides commissioning for data centers or mission critical facilities. Descriptions paraphrase or quote that site and are cited to the page we read; they are the companies' claims, which we haven't independently verified. The list is alphabetical, nothing is ranked, and no company paid to be listed or has any agreement with us. Firms we found but couldn't check this round (for example, one site returned a security-certificate error) are left out; being absent means nothing about a firm's quality. Companies can ask to be added or corrected through the contact page.

Ascent

Data centers, mission critical facilities and IT rooms

Says it provides data center commissioning “for every phase of data center design and construction” with teams led by AEE Certified Building Commissioning Professionals. Its listed tasks include OPR and basis of design, the commissioning plan, pre-functional checklists, startup verification, functional testing, training verification and seasonal or phased testing.21

Bureau Veritas North America (Primary Integration)

Data center services from design and construction to operations

Its North American data center page lists commissioning alongside design review, construction quality assurance and operational compliance, and links to Primary Integration, which it describes as supporting mission critical facilities worldwide, among its data center support services.22

Burns & McDonnell

Engineering, construction and commissioning

Its data center site describes an approach built on architecture, engineering, construction and commissioning. Its commissioning page says the service can be provided independently or bundled with its design and construction work, and that team members hold credentials from ACG, ASHRAE and USGBC.2324

CAI

Mission critical commissioning and operational readiness

Its Mission Critical group describes field-tested commissioning services and operational readiness work. A published case study covers commissioning an evaporative cooling retrofit and BAS upgrade at three operating hyperscale data centers in Dublin, Ireland.2526

CPG Beyond the Cloud

Data center services

Its commissioning and QA/QC page lists Level 1 factory witness testing, Level 2 site acceptance inspection, Level 3 pre-functional testing, Level 4 functional performance testing and Level 5 integrated systems testing.27

CXT Engineering

Critical systems commissioning

Lists critical systems commissioning at Levels 1 to 5, IST and IST script writing, retro-commissioning, metering verification, DC plant commissioning and remote power panel commissioning.10

HDR

Architecture and engineering

Says it manages and validates commissioning “from the earliest design stages through to the completion of complex integrated test procedures,” and lists commissioning among its data center services.2829

Intertek

Testing, inspection and certification

Says its data center commissioning includes functional testing, performance evaluation under load and documentation for turnover, plus power quality analysis, and that redundancy is checked against Tier-based design objectives.30

IPS

Commissioning, qualification and validation

Describes a program from Level 0 planning to Level 7 operational readiness, including Level 1+ modular factory testing and Level 5 electrical integrated, load bank and heat load testing. It says it provides independent commissioning as defined by USGBC LEED requirements, ACG, BCxA, ASHRAE Guideline 0-2019, NEBB and SMACNA documents.8

Salas O'Brien

Engineering and commissioning

Says it works “as a third-party independent team member” on commissioning and lists data center commissioning focused on power, cooling and network infrastructure.31

Syska Hennessy Group

Consulting engineers

Says it offers commissioning for performance verification for critical facilities. Its commissioning page lists new building commissioning of mechanical, electrical, life safety and integrated systems, plus retro-commissioning and monitoring-based commissioning.3233

Many electrical testing firms, OEM service groups and general contractors also run parts of commissioning, such as factory tests, start-up or electrical acceptance testing. They aren't listed here unless their own site describes data center commissioning.

Limits of this guide

This page summarizes published sources as they read on November 27, 2026. Level names and scope vary by firm and contract. We read ASHRAE's descriptions of Standard 202-2024 and Guideline 0-2019, not their full text, and Guideline 1.6P is unpublished, so its final content may differ from the planned sections reported in 2020. Load bank figures and the planner are planning aids, not engineering; your electrical engineer and load bank supplier size the test. The cost benchmark is for North American commercial buildings, not data centers. Directory entries are self-descriptions; we haven't verified licenses, insurance, experience or pricing for any firm, and listing isn't an endorsement.

What to send for a commissioning proposal

A commissioning firm can scope and price the work faster when it knows the facility, the stage you're at and which levels you want:

  • New build, expansion or retrofit, and the IT load in MW (initial and final phases).
  • Cooling type: air, liquid (direct-to-chip or rear door) or hybrid, and the expected split.
  • Electrical architecture at a high level: utility voltage, generator and UPS topology, redundancy target.
  • Levels you want the CxA to lead, witness or only review, and whether you need design-phase review.
  • Design stage and construction schedule, including planned turnover blocks and the target IST window.
  • Factory test locations, if known.
  • Whether you're pursuing Uptime Tier certification or another certification.
  • Your role (owner, developer or contractor) and who will hold the commissioning contract.

If you're leasing rather than building, the questions change: ask the colocation provider what commissioning and IST were done on your hall before you move in. Construct & Commission puts a deep clean of the data hall in its Level 6 turnover, if it wasn't done earlier;7 for scope, ISO cleanliness class and frequency see post-construction data center cleaning.

Request commissioning proposals through Data Center Service Providers

Send one request with your project details. A person reviews it and, where we can identify commissioning firms that fit the project, shares it with up to three of them. They aren't necessarily the companies in the directory above. We don't yet have agreements with any providers, so we can't promise how many will respond or how quickly. Any firm that does contacts you directly, and you decide whether to hire anyone. It's free for buyers. Providers who receive requests may in future pay us a referral fee; the referral disclosure explains how. We're a directory and referral service, not a commissioning agent, engineer or contractor, and routing a request isn't an endorsement. Read how requests are handled, or go to the request form.

Request commissioning proposals

Sources

  1. Commissioning & Performance Validation (AI Data Center Energy Performance Framework), ASHRAE. Level 1 to Level 5 definitions, schedule pressures and recommended practices. Checked 2026-11-27.
  2. Titles, Purposes, and Scopes (Guideline 1.6P, Commissioning of Data Centers), ASHRAE. Guideline 1.6P listed as a proposed guideline, approved November 4, 2017; revised TPS (title only) approved June 2024. Checked 2026-11-27.
  3. SSPC 300 Commissioning: Activities, ASHRAE Standing Standard Project Committee 300. Committee page listing the commissioning standards and guidelines, with purpose and scope text. Checked 2026-11-27.
  4. Commissioning (publications and certification), ASHRAE Bookstore. Current editions: Standard 202-2024, Guideline 0-2019, Standard 230-2022, Guideline 1.4-2019. Checked 2026-11-27.
  5. ASHRAE Guideline 1.6: Data Center Commissioning, ACHR News (Terry L. Rodgers), January 15, 2020. Planned section list of the proposed guideline. Checked 2026-11-27.
  6. Do you know the seven stages of data center commissioning?, JLL, February 17, 2025. Checked 2026-11-27.
  7. Data Center | 0, 1, 2, 3, 4, 5, 6 Levels of Commissioning, Construct & Commission (Bob Morris), Updated March 19, 2026. Practitioner guide; sells commissioning templates. Checked 2026-11-27.
  8. Commissioning Data Centers, IPS. Commissioning firm describing its own program. Also used for its directory entry. Checked 2026-11-27.
  9. Data center commissioning: The 5 levels of testing, CxPlanner (Thomas T. Jarloev), August 6, 2026. Commissioning software vendor. Checked 2026-11-27.
  10. Commissioning Services, CXT Engineering. Also used for its directory entry. Checked 2026-11-27.
  11. The Future of Data Center Commissioning (technical white paper), Universal Load Banks, November 2026. Load bank manufacturer. Checked 2026-11-27.
  12. Tier Certification: Construction (TCCF), Uptime Institute. Checked 2026-11-27.
  13. Lessons Learned from Tier Certification of Constructed Facilities, Uptime Institute Journal (Kevin Heslin), May 11, 2016. Checked 2026-11-27.
  14. ANSI/NETA ATS, Standard for Acceptance Testing Specifications for Electrical Power Equipment and Systems, InterNational Electrical Testing Association (NETA). Current edition shown: ATS-2025. Checked 2026-11-27.
  15. Certified Commissioning Authority (CxA) Certification, ACG: AABC Commissioning Group. Checked 2026-11-27.
  16. Certified Commissioning Professional (CCP), Building Commissioning Certification Board (BCCB). Checked 2026-11-27.
  17. Certification, Building Commissioning Association (BCxA). Checked 2026-11-27.
  18. BCxP: Building Commissioning Professional Certification, ASHRAE. Checked 2026-11-27.
  19. Building Systems Commissioning (BSC) Certification, NEBB. Checked 2026-11-27.
  20. Building commissioning costs and savings across three decades and 1500 North American buildings (Energy and Buildings, vol. 227), Crowe, Mills, Poeling, Curtin, Bjørnskov, Fischer and Granderson; Lawrence Berkeley National Laboratory and BCxA, August 26, 2020. Cost table read from the full text hosted by BCxA: https://www.bcxa.org/uploads/resources/LBNL%20Building%20Commissioning%20Cost%20and%20Savings%20Across%20Two%20Decades%20and%201,500%20Projects.pdf Checked 2026-11-27.
  21. Ascent's Data Center Commissioning Services, Ascent. Checked 2026-11-27.
  22. North America Data Centers, Bureau Veritas North America. Checked 2026-11-27.
  23. Integrated Solutions for Data Centers, Burns & McDonnell. Checked 2026-11-27.
  24. Commissioning, Burns & McDonnell. Checked 2026-11-27.
  25. Mission Critical, CAI. Checked 2026-11-27.
  26. Data Center Commissioning in a Live Environment (case study), CAI. Checked 2026-11-27.
  27. Data Center Commissioning & QA/QC, CPG Beyond the Cloud. Checked 2026-11-27.
  28. Commissioning & Operations, HDR. Checked 2026-11-27.
  29. Data Centers, HDR. Checked 2026-11-27.
  30. Data Center Services, Intertek. Checked 2026-11-27.
  31. Commissioning, Salas O'Brien. Checked 2026-11-27.
  32. Critical Facilities, Syska Hennessy Group. Checked 2026-11-27.
  33. Commissioning, Syska Hennessy Group. Checked 2026-11-27.